How soon can you start building my swimming pool?

How soon can you start building my swimming pool?

Update: 3/5/2021

The information in this article is based on, and how the building and construction industry has been for years. During Covid we have had even longer delays on EVERYTHING. Some building departments LOVE Covid and are taking advantage of the situation. The city of Columbus right now is taking up to 9 weeks just to receive an application. They claim it is for quarantining and short staffing. Up until spring 2020 you could walk in and walk out with a permit same day. THE LAZY Love Covid and the City of Columbus has become the posterchild.

Building supply costs are on the rise. In most situations 30%-40% from 2019 and Q1 2020. In some cases such as electric and PVC plumbing the costs have DOUBLED. This is assuming you can put your hands on the materials you need. We have found that some materials and pool related components are out as far as 6 months just to get the components. Most pool suppliers / factories are out 9 months right now on pools themselves. Covid has developed into the perfect storm of HIGH DEMAND and shallow supply.

There are almost no pool components in "Stock." As an industry we hope to get back to that material flow with inventory in the pipeline. It may be a year or more before that occurs. As if Covid wasn't enough, the Texas deep freeze earlier this year gave the pool industry a second major blow. Texas doesn't winterize pools and don't know how to deal with the cold. There are reports of as many as 90% of all pools in Texas need new pumps, filters, chlorinators, valves, EVERYTHING due to freeze damage. The US pool market already was not able to support new pools installations. Now that just about every pool in TX needs rebuilt we expect even further complications with getting components and supplies.

Original Article -

"So how far out are you scheduling right now?" Asked an excited pool owner to be. "It depends" I replied. Many people ask how many pools we have in queue and where they would end up on the list. The truth however is that we don’t operate (as it would be totally impossible) on a "first in first out" basis. There is a chance that your project could be a lot quicker than simply going to the end of the line. Once we have all the components we need we get started!

EXAMPLE: If you select a pool that is in stock, have an easy building department or even no building department at all, AND your site is dry and ready! You go to the front of the line.

Permits

fiberglass swimming pool permit pack
If your permits require this much
paperwork, it could take a while.

If you live in an area that requires a long drawn out zoning process, and have a matching uncooperative building department it is very difficult to tell you exactly how long it's going to take to get your permit. That's not us dodging you and not wanting to get pinned down, it's just the truth. Several years ago we had four pools take over nine weeks to get permits. I can't explain why, it just did. In some departments for no reason other than they are just slow and in others they have written zoning and building codes to discourage pools. I have a permit right now that took eight weeks in Cincinnati. The project is similar to those we have obtained in just two weeks. To add insult to injury this particular project consisted of us installing one of our fiberglass pools inside of a larger existing concrete pool. Of all projects this should have been a pretty straightforward approval. Cincinnati offered us no explanation.

Pool Availability

If at all possible looking at pool models and colors in stock makes the most sense if timing is a concern to you. If you happen to select a pool model that is not in stock and needs to be built special order it may take us two to eight weeks depending on where we are in the shipping schedule. This is because we receive a semi-truck ever couple weeks. Each load is a stack of similar models. This week may be Moroccans and / or Riveras the next may be Elegances. If you order a special order Moroccan today, I may not actually get another truck of Moroccans for several weeks or longer.

Site Conditions

fiberglass pool weather forecast
On average it takes three days of good
weather to dry up for one day of rain.

This is simple and somewhat obvious but needs to mentioned. If you have a power line that needs to be moved or trees that need cut down, we need to make sure those items are done BEFORE we schedule the install.

Weather

Last but not least. Weather is without a doubt the most complicated variable we work around. When it rains and the ground is wet, it is very hard if not in most cases impossible to get on the ground and work. Even though we only need a few day to our work, a days worth of rain can need three to four days to dry out and brings most of our production to a stop. Please keep in mind that when we get a few weeks of rain our whole schedule gets pushed back several weeks.

Hopefully this has shed some light some of the variables associated with the timing of a pool project. These variables are not unique to our company. All outdoor construction is affected in similar ways. Unfortunately however sometimes customers are told what they want to hear NOT the whole truth and why.

1605 Shawnee Ave, Columbus, OH 43211 | Columbus (614) 890-7665
11470 Hawke Rd, Columbia Station, OH 44028 | Cleveland (440) 237-7665
9295 Franklin Rd, Murfreesboro, TN 37128 | Nashville (615) 900-2181
Copyright Luxury Pools and Living 2005-2021